← Back to Tavnit

Sample permit roadmap

Sample permit roadmap

Direct lithium extraction from brine · Northeast Texas · Smackover Formation · Illustrative example

9

steps

6

agencies

~20 months

to earliest construction start

Injection wells

critical path

SEQUENCE / CRITICAL PATH

Critical path

Parallel

If applicable

Risk

MONTHS FROM KICKOFF

M0

M4

M8

M12

M16

M20

M24

PREPARE

Earliest construction start · ~M20

Brine rights & leasing

Risk

Reservoir test well & brine data

STATE REVIEW

Brine production project permit

Class V spent-brine injection wells

Risk

Air permit for processing plant

Water supply permit

FEDERAL & LOCAL

Section 404 wetlands permit

If applicable

Construction stormwater authorization

County floodplain & road use permits

Scroll horizontally to explore the full timeline. Hover or tap a bar for details.

WHAT TAVNIT FLAGS

Two agencies, one well

Spent-brine injection wells may need both state and EPA approval. File with both early. This is the critical path.

Settle brine rights first

Texas law on brine ownership and royalties is still evolving. Unclear rights can stall everything downstream.

Run in parallel

Air and water supply permits can advance while reservoir data is still being collected.

ALL REQUIREMENTS

Permit

Agency

Level

Triggered by

Typical duration

Depends on

PRE-PERMIT

Brine rights & leasing

Private landowners

Private

Securing brine ownership, leases, and royalties

6–9 mo

None — begin at kickoff

Reservoir test well & brine data

Railroad Commission of Texas

State

Testing the reservoir and collecting brine data

6–9 mo

Initial brine rights / site access

STATE

Brine production project permit

Railroad Commission of Texas

State

Producing brine to extract minerals

4–6 mo

Reservoir test well & brine data

Class V spent-brine injection wells

Railroad Commission of Texas + EPA Region 6

State

Returning spent brine underground

6–9 mo

Reservoir test well & brine data

Air permit for processing plant

TCEQ

State

Emissions from the processing plant

6–9 mo

Plant design and emissions estimates

Illustrative only. Actual requirements and timelines depend on site conditions and agency review.